Solar permits in New Orleans, LA

Data through September 2026 · updated 18 Oct 2026

1,046 solar permits were issued in New Orleans, October 2024 through September 2026: about 523 a year and 4% of all permits. 166 solar permits in the last 12 months (Oct 2025–Sep 2026), 81% fewer than the 880 in the 12 months before. The busiest month is October. The usual one took 63 days from issue to the city's final. 70122 has the most, 181.

1,046permits issued
166last 12 months
Octbusiest month
63days, usual issue to final
73%finished
$29,597usual declared value
Sep 2026records through

Solar permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 119Oct2024Nov 2024: 90Dec 2024: 34Jan 2025: 84Jan2025Feb 2025: 113Mar 2025: 55Apr 2025: 144May 2025: 72Jun 2025: 61Jul 2025: 29JulAug 2025: 68Sep 2025: 11Oct 2025: 32Nov 2025: 19Dec 2025: 34Jan 2026: 20Jan2026Feb 2026: 7Mar 2026: 27Apr 2026: 5May 2026: 10Jun 2026: 2Jul 2026: 2JulAug 2026: 4Sep 2026: 4
The same numbers as a table
MonthPermits
Oct 2024119
Nov 202490
Dec 202434
Jan 202584
Feb 2025113
Mar 202555
Apr 2025144
May 202572
Jun 202561
Jul 202529
Aug 202568
Sep 202511
Oct 202532
Nov 202519
Dec 202534
Jan 202620
Feb 20267
Mar 202627
Apr 20265
May 202610
Jun 20262
Jul 20262
Aug 20264
Sep 20264

Download this table (CSV)

When solar permits are filed

By calendar month, 100 = an average month (the thin line). October is the busiest (173), September the quietest (17). A busy month at the permit counter usually means a longer wait for a contractor.

January: 119 (100 = an average month)February: 138 (100 = an average month)March: 94 (100 = an average month)April: 171 (100 = an average month)May: 94 (100 = an average month)June: 72 (100 = an average month)July: 36 (100 = an average month)August: 83 (100 = an average month)September: 17 (100 = an average month)October: 173 (100 = an average month)173November: 125 (100 = an average month)December: 78 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January119
February138
March94
April171
May94
June72
July36
August83
September17
October173
November125
December78

Download this table (CSV)

How long a solar permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 587 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025880
Finished73.3%
Expired0.2%
Usual days, issue to final63
Middle half, days41–115

Download this table (CSV)

What a solar permit is declared at

The value written on the permit at application, from 1,045 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$29,597
Middle half$18,900–$46,332

Download this table (CSV)

ZIP codes with the most solar permits

Counted at the property's ZIP code. Share is the part of the city's 1,046 solar permits.

ZIP codePermitsShare
7012218117%
7011713913%
70119929%
70126899%
70127838%
70115808%
70128707%
70118697%
70131575%
70124404%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
SolarAPP+48546%
Solar28627%
Renovation (Non-Structural)22922%
Solar Commercial or Modification (Any Land-Use)333%
Renovation (Structural)10under 1%
Accessory Structure2under 1%
Renovation (Structural or Non-structural)1under 1%

Download this table (CSV)

How New Orleans compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of New Orleans, Permits - BLDS (data.nola.gov, dataset 72f9-bi28), read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential permits the City of New Orleans Department of Safety and Permits issues inside the city, which is also Orleans Parish: building, renovation, re-roofing, electrical, plumbing, gas, HVAC, solar, pool, generator and demolition permits for single-family homes, two-family homes and doubles. Permits for buildings with three or more units and commercial property are not counted, nor are historic-district reviews, right-of-way permits (street cuts, driveways, sidewalks) and address changes in the same file. Jefferson, St. Bernard and St. Tammany parishes run their own permit offices and are not in this file.

  • The city's file lists a contractor on most permits, usually the licensed person rather than the company, but these pages show permit counts only: there are no contractor lists, rankings or firm pages for New Orleans.
  • The value is the project cost declared on the application. About a third of permits carry none, mostly small trade permits.
  • Gas permits (gas lines, water heaters and the six-month gas test after a home sits empty) are counted with plumbing; an electrical vacancy permit, needed to turn power back on in a home that sat empty, counts as electrical.
  • The city's file has a residential re-roofing permit type only from May 2025; before that few re-roofs appear in it, so the rise in roofing permits mostly reflects the new permit type, not more roofs.
  • A final date is the day the city recorded the permit as finaled or completed. Permits the city marks Closed count as finished but add no days, because the file does not say whether the work passed a final inspection.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Solar permits in New Orleans, LA", https://contractorrecords.com/new-orleans/solar-permits, data through September 2026, from the City of New Orleans Department of Safety and Permits building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code · Permit types.

Download the tables (CSV): Solar permits by month · Solar permits by calendar month (index) · Solar permits: days to final · Solar permits: declared value · Solar permits by ZIP code · Solar permits by permit type.

Common questions

  • How many solar permits does New Orleans issue a year?About 523 a year in New Orleans: 1,046 permits issued October 2024 through September 2026, 166 of them in the last 12 months.
  • How long does a solar permit take in New Orleans?The usual one took 63 days from issue to the city's final inspection, and the middle half took 41 to 115 days (587 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in New Orleans file the most solar permits?October (173 against an average month of 100); September is the quietest (17). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most solar permits in New Orleans?70122, with 181 of the 1,046 (17%); then 70117 (139).