Electrical permits in New Orleans, LA

Data through September 2026 · updated 18 Oct 2026

9,668 electrical permits were issued in New Orleans, October 2024 through September 2026: about 4,834 a year and 35% of all permits. 4,752 electrical permits in the last 12 months (Oct 2025–Sep 2026), 3% fewer than the 4,916 in the 12 months before. The busiest month is June. The usual one took 47 days from issue to the city's final. 70115 has the most, 1,103.

9,668permits issued
4,752last 12 months
Junbusiest month
47days, usual issue to final
74%finished
$4,625usual declared value
Sep 2026records through

Electrical permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 458Oct2024Nov 2024: 282Dec 2024: 334Jan 2025: 309Jan2025Feb 2025: 306Mar 2025: 298Apr 2025: 465May 2025: 412Jun 2025: 567Jul 2025: 552JulAug 2025: 549Sep 2025: 384Oct 2025: 470Nov 2025: 303Dec 2025: 336Jan 2026: 325Jan2026Feb 2026: 379Mar 2026: 388Apr 2026: 336May 2026: 564Jun 2026: 427Jul 2026: 431JulAug 2026: 389Sep 2026: 404
The same numbers as a table
MonthPermits
Oct 2024458
Nov 2024282
Dec 2024334
Jan 2025309
Feb 2025306
Mar 2025298
Apr 2025465
May 2025412
Jun 2025567
Jul 2025552
Aug 2025549
Sep 2025384
Oct 2025470
Nov 2025303
Dec 2025336
Jan 2026325
Feb 2026379
Mar 2026388
Apr 2026336
May 2026564
Jun 2026427
Jul 2026431
Aug 2026389
Sep 2026404

Download this table (CSV)

When electrical permits are filed

By calendar month, 100 = an average month (the thin line). June is the busiest (123), November the quietest (73). A busy month at the permit counter usually means a longer wait for a contractor.

January: 79 (100 = an average month)February: 85 (100 = an average month)March: 85 (100 = an average month)April: 99 (100 = an average month)May: 121 (100 = an average month)June: 123 (100 = an average month)123July: 122 (100 = an average month)August: 116 (100 = an average month)September: 98 (100 = an average month)October: 115 (100 = an average month)November: 73 (100 = an average month)December: 83 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January79
February85
March85
April99
May121
June123
July122
August116
September98
October115
November73
December83

Download this table (CSV)

How long an electrical permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 3,232 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 20254,916
Finished74.2%
Expired1.6%
Usual days, issue to final47
Middle half, days20–130

Download this table (CSV)

What an electrical permit is declared at

The value written on the permit at application, from 9,557 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$4,625
Middle half$960–$14,573

Download this table (CSV)

ZIP codes with the most electrical permits

Counted at the property's ZIP code. Share is the part of the city's 9,668 electrical permits.

ZIP codePermitsShare
701151,10311%
701181,09211%
701229149%
701178859%
701248208%
701197978%
701146226%
701265626%
701315596%
701254875%

Download this table (CSV)

The city's own permit types

How the city filed these permits. We group its types into kinds of work; this is the split.

Permit typePermitsShare
Electrical Service / Circuit / Feeder4,54047%
Electrical Vacancy1,46915%
Construction Loop8949%
Electrical Repair / Replacement / Addition8569%
Mechanical Fuel Gas7418%
Permanent Generator5826%
Accessory Structure4965%
Electric Vehicle Charger: Electrical51under 1%
Electric Vehicle Charger: Installation20under 1%
Renovation (Structural)14under 1%

Download this table (CSV)

How New Orleans compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of New Orleans, Permits - BLDS (data.nola.gov, dataset 72f9-bi28), read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential permits the City of New Orleans Department of Safety and Permits issues inside the city, which is also Orleans Parish: building, renovation, re-roofing, electrical, plumbing, gas, HVAC, solar, pool, generator and demolition permits for single-family homes, two-family homes and doubles. Permits for buildings with three or more units and commercial property are not counted, nor are historic-district reviews, right-of-way permits (street cuts, driveways, sidewalks) and address changes in the same file. Jefferson, St. Bernard and St. Tammany parishes run their own permit offices and are not in this file.

  • The city's file lists a contractor on most permits, usually the licensed person rather than the company, but these pages show permit counts only: there are no contractor lists, rankings or firm pages for New Orleans.
  • The value is the project cost declared on the application. About a third of permits carry none, mostly small trade permits.
  • Gas permits (gas lines, water heaters and the six-month gas test after a home sits empty) are counted with plumbing; an electrical vacancy permit, needed to turn power back on in a home that sat empty, counts as electrical.
  • The city's file has a residential re-roofing permit type only from May 2025; before that few re-roofs appear in it, so the rise in roofing permits mostly reflects the new permit type, not more roofs.
  • A final date is the day the city recorded the permit as finaled or completed. Permits the city marks Closed count as finished but add no days, because the file does not say whether the work passed a final inspection.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "Electrical permits in New Orleans, LA", https://contractorrecords.com/new-orleans/electrical-permits, data through September 2026, from the City of New Orleans Department of Safety and Permits building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code · Permit types.

Download the tables (CSV): Electrical permits by month · Electrical permits by calendar month (index) · Electrical permits: days to final · Electrical permits: declared value · Electrical permits by ZIP code · Electrical permits by permit type.

Common questions

  • How many electrical permits does New Orleans issue a year?About 4,834 a year in New Orleans: 9,668 permits issued October 2024 through September 2026, 4,752 of them in the last 12 months.
  • How long does an electrical permit take in New Orleans?The usual one took 47 days from issue to the city's final inspection, and the middle half took 20 to 130 days (3,232 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in New Orleans file the most electrical permits?June (123 against an average month of 100); November is the quietest (73). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most electrical permits in New Orleans?70115, with 1,103 of the 9,668 (11%); then 70118 (1,092).