New home permits in New Orleans, LA

Data through September 2026 · updated 18 Oct 2026

717 new home permits were issued in New Orleans, October 2024 through September 2026: about 358 a year and 3% of all permits. 385 new home permits in the last 12 months (Oct 2025–Sep 2026), 16% more than the 332 in the 12 months before. The busiest month is July. The usual one took 272 days from issue to the city's final. 70122 has the most, 64.

717permits issued
385last 12 months
Julbusiest month
272days, usual issue to final
78%finished
$268,340usual declared value
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 34Oct2024Nov 2024: 22Dec 2024: 18Jan 2025: 15Jan2025Feb 2025: 25Mar 2025: 19Apr 2025: 23May 2025: 26Jun 2025: 22Jul 2025: 67JulAug 2025: 37Sep 2025: 24Oct 2025: 59Nov 2025: 30Dec 2025: 22Jan 2026: 37Jan2026Feb 2026: 26Mar 2026: 41Apr 2026: 30May 2026: 24Jun 2026: 30Jul 2026: 29JulAug 2026: 27Sep 2026: 30
The same numbers as a table
MonthPermits
Oct 202434
Nov 202422
Dec 202418
Jan 202515
Feb 202525
Mar 202519
Apr 202523
May 202526
Jun 202522
Jul 202567
Aug 202537
Sep 202524
Oct 202559
Nov 202530
Dec 202522
Jan 202637
Feb 202626
Mar 202641
Apr 202630
May 202624
Jun 202630
Jul 202629
Aug 202627
Sep 202630

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). July is the busiest (161), December the quietest (67). A busy month at the permit counter usually means a longer wait for a contractor.

January: 87 (100 = an average month)February: 85 (100 = an average month)March: 100 (100 = an average month)April: 89 (100 = an average month)May: 84 (100 = an average month)June: 87 (100 = an average month)July: 161 (100 = an average month)161August: 107 (100 = an average month)September: 90 (100 = an average month)October: 156 (100 = an average month)November: 87 (100 = an average month)December: 67 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January87
February85
March100
April89
May84
June87
July161
August107
September90
October156
November87
December67

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 257 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025332
Finished78.0%
Expired0.0%
Usual days, issue to final272
Middle half, days199–348

Download this table (CSV)

What a new home permit is declared at

The value written on the permit at application, from 713 permits with one. Not a quote and not the final bill.

MeasureValue
Usual declared value$268,340
Middle half$197,003–$385,600

Download this table (CSV)

ZIP codes with the most new home permits

Counted at the property's ZIP code. Share is the part of the city's 717 new home permits.

ZIP codePermitsShare
70122649%
70124608%
70126416%
70112365%
70127355%
70117345%
70115294%
70114274%
70118213%
70131213%

Download this table (CSV)

How New Orleans compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of New Orleans, Permits - BLDS (data.nola.gov, dataset 72f9-bi28), read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential permits the City of New Orleans Department of Safety and Permits issues inside the city, which is also Orleans Parish: building, renovation, re-roofing, electrical, plumbing, gas, HVAC, solar, pool, generator and demolition permits for single-family homes, two-family homes and doubles. Permits for buildings with three or more units and commercial property are not counted, nor are historic-district reviews, right-of-way permits (street cuts, driveways, sidewalks) and address changes in the same file. Jefferson, St. Bernard and St. Tammany parishes run their own permit offices and are not in this file.

  • The city's file lists a contractor on most permits, usually the licensed person rather than the company, but these pages show permit counts only: there are no contractor lists, rankings or firm pages for New Orleans.
  • The value is the project cost declared on the application. About a third of permits carry none, mostly small trade permits.
  • Gas permits (gas lines, water heaters and the six-month gas test after a home sits empty) are counted with plumbing; an electrical vacancy permit, needed to turn power back on in a home that sat empty, counts as electrical.
  • The city's file has a residential re-roofing permit type only from May 2025; before that few re-roofs appear in it, so the rise in roofing permits mostly reflects the new permit type, not more roofs.
  • A final date is the day the city recorded the permit as finaled or completed. Permits the city marks Closed count as finished but add no days, because the file does not say whether the work passed a final inspection.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in New Orleans, LA", https://contractorrecords.com/new-orleans/new-home-permits, data through September 2026, from the City of New Orleans Department of Safety and Permits building-permit records.

Link to a table: By month · Season · Days to final · Declared value · By ZIP code.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits: declared value · New homes permits by ZIP code.

Common questions

  • How many new home permits does New Orleans issue a year?About 358 a year in New Orleans: 717 permits issued October 2024 through September 2026, 385 of them in the last 12 months.
  • How long does a new home permit take in New Orleans?The usual one took 272 days from issue to the city's final inspection, and the middle half took 199 to 348 days (257 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in New Orleans file the most new home permits?July (161 against an average month of 100); December is the quietest (67). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most new home permits in New Orleans?70122, with 64 of the 717 (9%); then 70124 (60).