How long do permits take in Virginia Beach, VA?

Data through September 2026 · updated 18 Oct 2026

The usual permit in Virginia Beach takes 37 days from issue to the city's final inspection; the middle half take 11 to 117 days. That is from 13,185 permits issued Oct 2024–Sep 2025 that reached a final. Demolition permits are quickest at 14 days; new home permits take longest at 248 days. This is the time to finish the work and close the permit, not the wait for approval.

37days, usual issue to final
11–117days, middle half
81%finished
13,185permits with a final date
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve the plans. Ask the city for its current review times.

Finishing the work (measured here): issue → final. From the day the city issued the permit to the day it recorded the final inspection. We count only permits issued Oct 2024–Sep 2025, at least 12 months before the file ends, so slow jobs have had time to finish; a permit still open is not in the days.

By kind of work

Permits issued Oct 2024–Sep 2025. Usual days is the middle permit among those with a final date: half finished sooner, half later. Middle half is the range the middle 50% fell in. Kinds of work with fewer than 100 permits in that period are left out.

Kind of workPermitsFinishedExpiredUsual days to finalMiddle half (days)
Plumbing4,13186.5%0.0%216–107
HVAC3,72372.8%0.0%4212–120
Electrical3,33786.7%0.1%328–111
Remodels & repairs1,99076.6%0.1%3914–107
Solar1,26794.6%0.2%3421–51
Additions55269.9%0.2%13365–238
Pools & spas45762.4%0.0%14769–238
Roofing30861.0%0.0%4222–87
New homes24984.3%0.4%248193–344
Demolition18495.1%0.0%147–34
Garages, sheds & shade structures12467.7%0.0%14060–216
Other31660.1%2.2%4823–100

Download this table (CSV)

How long each kind of permit takes

Each kind of work on its own, issue to the city's final.

How long does plumbing work take in Virginia Beach, from permit to final?

The usual plumbing permit in Virginia Beach takes 21 days from issue to final; the middle half take 6 to 107 days (3,516 permits with a final date, issued Oct 2024–Sep 2025). 86% of the 4,131 permits issued then have finished and 0% expired. Virginia Beach plumbing permits →

How long does an HVAC replacement take in Virginia Beach, from permit to final?

The usual HVAC permit in Virginia Beach takes 42 days from issue to final; the middle half take 12 to 120 days (2,669 permits with a final date, issued Oct 2024–Sep 2025). 73% of the 3,723 permits issued then have finished and 0% expired. Virginia Beach HVAC permits →

How long does electrical work take in Virginia Beach, from permit to final?

The usual electrical permit in Virginia Beach takes 32 days from issue to final; the middle half take 8 to 111 days (2,858 permits with a final date, issued Oct 2024–Sep 2025). 87% of the 3,337 permits issued then have finished and under 1% expired. Virginia Beach electrical permits →

How long does a remodel take in Virginia Beach, from permit to final?

The usual remodel and repair permit in Virginia Beach takes 39 days from issue to final; the middle half take 14 to 107 days (1,495 permits with a final date, issued Oct 2024–Sep 2025). 77% of the 1,990 permits issued then have finished and under 1% expired. Virginia Beach remodel and repair permits →

How long does a solar installation take in Virginia Beach, from permit to final?

The usual solar permit in Virginia Beach takes 34 days from issue to final; the middle half take 21 to 51 days (1,133 permits with a final date, issued Oct 2024–Sep 2025). 95% of the 1,267 permits issued then have finished and under 1% expired. Virginia Beach solar permits →

How long does a home addition take in Virginia Beach, from permit to final?

The usual home addition permit in Virginia Beach takes 133 days from issue to final; the middle half take 65 to 238 days (382 permits with a final date, issued Oct 2024–Sep 2025). 70% of the 552 permits issued then have finished and under 1% expired. Virginia Beach home addition permits →

How long does a pool or spa take in Virginia Beach, from permit to final?

The usual pool and spa permit in Virginia Beach takes 147 days from issue to final; the middle half take 69 to 238 days (280 permits with a final date, issued Oct 2024–Sep 2025). 62% of the 457 permits issued then have finished and 0% expired. Virginia Beach pool and spa permits →

How long does a roof replacement take in Virginia Beach, from permit to final?

The usual roofing permit in Virginia Beach takes 42 days from issue to final; the middle half take 22 to 87 days (186 permits with a final date, issued Oct 2024–Sep 2025). 61% of the 308 permits issued then have finished and 0% expired. Virginia Beach roofing permits →

How long does building a new home take in Virginia Beach, from permit to final?

The usual new home permit in Virginia Beach takes 248 days from issue to final; the middle half take 193 to 344 days (207 permits with a final date, issued Oct 2024–Sep 2025). 84% of the 249 permits issued then have finished and under 1% expired. Virginia Beach new home permits →

How long does a demolition take in Virginia Beach, from permit to final?

The usual demolition permit in Virginia Beach takes 14 days from issue to final; the middle half take 7 to 34 days (173 permits with a final date, issued Oct 2024–Sep 2025). 95% of the 184 permits issued then have finished and 0% expired. Virginia Beach demolition permits →

How long does a garage, shed or patio cover take in Virginia Beach, from permit to final?

The usual garage, shed and shade structure permit in Virginia Beach takes 140 days from issue to final; the middle half take 60 to 216 days (84 permits with a final date, issued Oct 2024–Sep 2025). 68% of the 124 permits issued then have finished and 0% expired. Virginia Beach garage, shed and shade structure permits →

How Virginia Beach compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Virginia Beach Open Data, Building Permits Applications (data.virginiabeach.gov, ArcGIS layer Building_Permits_Applications_view), read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential permits the City of Virginia Beach issues inside the city: building, electrical, mechanical, plumbing and gas permits for homes, plus the city's roof and siding permits. Commercial permits, moving and hauling, utility, civil site work, fire, elevator and amusement permits in the same file are not counted. Norfolk, Chesapeake and the other Hampton Roads cities run their own permit offices and are not in this file.

  • The city's file names no contractor (its 'created by' field is a portal login), so there are no contractor lists, rankings or firm pages for Virginia Beach.
  • The file has no declared job value, so we show no costs.
  • Roof and siding permits are their own type in the file, with no homes-or-business split, so all of them are counted here. Solar, pools, fences, additions and sheds are sorted out of the city's broad 'addition and or alteration' building permits by their work description; decks, piers and bulkheads count under Other.
  • A permit counts as finished when the city marks it Final or Closed or gives it a final date. Closed also covers permits that needed no final inspection.
  • The data made available here has been modified for use from its original source, which is the City of Virginia Beach. Neither the City of Virginia Beach nor the Office of the Chief Information Officer (CIO) makes any claims as to the completeness, timeliness, accuracy or content of any data contained in this application; makes any representation of any kind, including, but not limited to, warranty of the accuracy or fitness for a particular use; nor are any such warranties to be implied or inferred with respect to the information or data furnished herein. The data is subject to change as modifications and updates are complete. It is understood that the information contained in the web feed is being used at one's own risk.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "How long do permits take in Virginia Beach, VA?", https://contractorrecords.com/virginia-beach/how-long-does-a-permit-take, data through September 2026, from the City of Virginia Beach Planning Department, Permits Division building-permit records.

Link to a table: By kind of work · Each kind of permit.

Download the tables (CSV): Days to final by kind of work.

Common questions

  • What is the permit turnaround in Virginia Beach?From issue to final inspection, the usual permit takes 37 days (middle half 11 to 117 days), from 13,185 permits issued Oct 2024–Sep 2025. The wait to get a permit issued is not in this file; ask the city for its current review times.
  • Which permits finish fastest in Virginia Beach?Demolition permits, at 14 days. The slowest are new home permits, at 248 days. Bigger jobs take longer; so does work where the final inspection is easy to forget.
  • How many permits actually get finished in Virginia Beach?81% of the 16,658 permits issued Oct 2024–Sep 2025 have finished; under 1% expired without a final and the rest are still open.
  • Why does an open permit matter to me?An unfinished permit stays with the property, not the contractor. It can hold up a sale or a refinance. Ask whoever does the work to call for the final inspection and show you the result.