New home permits in Virginia Beach, VA

Data through September 2026 · updated 18 Oct 2026

472 new home permits were issued in Virginia Beach, October 2024 through September 2026: about 236 a year and 1% of all permits. 223 new home permits in the last 12 months (Oct 2025–Sep 2026), 10% fewer than the 249 in the 12 months before. The busiest month is March. The usual one took 248 days from issue to the city's final. 23451 has the most, 180.

472permits issued
223last 12 months
Marbusiest month
248days, usual issue to final
84%finished
Sep 2026records through

New home permits by month

Permits issued each month, October 2024 through September 2026.

Oct 2024: 17Oct2024Nov 2024: 15Dec 2024: 16Jan 2025: 19Jan2025Feb 2025: 22Mar 2025: 29Apr 2025: 23May 2025: 23Jun 2025: 25Jul 2025: 25JulAug 2025: 17Sep 2025: 18Oct 2025: 16Nov 2025: 30Dec 2025: 16Jan 2026: 17Jan2026Feb 2026: 17Mar 2026: 23Apr 2026: 16May 2026: 26Jun 2026: 15Jul 2026: 16JulAug 2026: 21Sep 2026: 10
The same numbers as a table
MonthPermits
Oct 202417
Nov 202415
Dec 202416
Jan 202519
Feb 202522
Mar 202529
Apr 202523
May 202523
Jun 202525
Jul 202525
Aug 202517
Sep 202518
Oct 202516
Nov 202530
Dec 202516
Jan 202617
Feb 202617
Mar 202623
Apr 202616
May 202626
Jun 202615
Jul 202616
Aug 202621
Sep 202610

Download this table (CSV)

When new home permits are filed

By calendar month, 100 = an average month (the thin line). March is the busiest (132), September the quietest (71). A busy month at the permit counter usually means a longer wait for a contractor.

January: 92 (100 = an average month)February: 99 (100 = an average month)March: 132 (100 = an average month)132April: 99 (100 = an average month)May: 125 (100 = an average month)June: 102 (100 = an average month)July: 104 (100 = an average month)August: 97 (100 = an average month)September: 71 (100 = an average month)October: 84 (100 = an average month)November: 114 (100 = an average month)December: 81 (100 = an average month)JFMAMJJASOND
The same numbers as a table
MonthIndex
January92
February99
March132
April99
May125
June102
July104
August97
September71
October84
November114
December81

Download this table (CSV)

How long a new home permit takes

Permits issued Oct 2024–Sep 2025, at least 12 months before the file ends. Usual days is the middle permit among the 207 with a final date.

MeasureValue
Permits issued Oct 2024–Sep 2025249
Finished84.3%
Expired0.4%
Usual days, issue to final248
Middle half, days193–344

Download this table (CSV)

ZIP codes with the most new home permits

Counted at the property's ZIP code. Share is the part of the city's 472 new home permits.

ZIP codePermitsShare
2345118038%
234569821%
234546013%
234524910%
23455317%
23457255%
23464163%
2346261%
234533under 1%

Download this table (CSV)

How Virginia Beach compares with other cities

From our cross-city data studies: the same measure, read the same way, for every city we cover.

How these numbers are made

Source: City of Virginia Beach Open Data, Building Permits Applications (data.virginiabeach.gov, ArcGIS layer Building_Permits_Applications_view), read 18 Oct 2026. We count permits issued October 2024 through September 2026; denied and withdrawn permits are left out.

Residential permits the City of Virginia Beach issues inside the city: building, electrical, mechanical, plumbing and gas permits for homes, plus the city's roof and siding permits. Commercial permits, moving and hauling, utility, civil site work, fire, elevator and amusement permits in the same file are not counted. Norfolk, Chesapeake and the other Hampton Roads cities run their own permit offices and are not in this file.

  • The city's file names no contractor (its 'created by' field is a portal login), so there are no contractor lists, rankings or firm pages for Virginia Beach.
  • The file has no declared job value, so we show no costs.
  • Roof and siding permits are their own type in the file, with no homes-or-business split, so all of them are counted here. Solar, pools, fences, additions and sheds are sorted out of the city's broad 'addition and or alteration' building permits by their work description; decks, piers and bulkheads count under Other.
  • A permit counts as finished when the city marks it Final or Closed or gives it a final date. Closed also covers permits that needed no final inspection.
  • The data made available here has been modified for use from its original source, which is the City of Virginia Beach. Neither the City of Virginia Beach nor the Office of the Chief Information Officer (CIO) makes any claims as to the completeness, timeliness, accuracy or content of any data contained in this application; makes any representation of any kind, including, but not limited to, warranty of the accuracy or fitness for a particular use; nor are any such warranties to be implied or inferred with respect to the information or data furnished herein. The data is subject to change as modifications and updates are complete. It is understood that the information contained in the web feed is being used at one's own risk.

Counts are permits, not jobs: one job can need several permits. Nobody paid to be on this page and nobody can. Sources and definitions →

Cite this page

Free to reuse with attribution (CC BY 4.0). Please credit Contractor Records and link to this page. Suggested citation:

Contractor Records, "New home permits in Virginia Beach, VA", https://contractorrecords.com/virginia-beach/new-home-permits, data through September 2026, from the City of Virginia Beach Planning Department, Permits Division building-permit records.

Link to a table: By month · Season · Days to final · By ZIP code.

Download the tables (CSV): New homes permits by month · New homes permits by calendar month (index) · New homes permits: days to final · New homes permits by ZIP code.

Common questions

  • How many new home permits does Virginia Beach issue a year?About 236 a year in Virginia Beach: 472 permits issued October 2024 through September 2026, 223 of them in the last 12 months.
  • How long does a new home permit take in Virginia Beach?The usual one took 248 days from issue to the city's final inspection, and the middle half took 193 to 344 days (207 permits issued Oct 2024–Sep 2025 that reached a final). The wait to get the permit issued is not in this file.
  • When do people in Virginia Beach file the most new home permits?March (132 against an average month of 100); September is the quietest (71). If you can choose, a quiet month at the permit counter can mean contractors have more room in their schedules.
  • Which ZIP code has the most new home permits in Virginia Beach?23451, with 180 of the 472 (38%); then 23456 (98).