How long do permits take in Cambridge, MA?

The usual electrical permit in Cambridge, the biggest trade with a completion date, takes 104 days from issue to the city's final inspection or closeout (3,820 permits, October 2023 through September 2026). Roofing is quickest at 17 days; demolition the slowest at 697 days. This is the turnaround to finish the work and close the permit, not the wait for approval.

120days, usual across trades
104days, usual electrical permit
72%electrical permits finished
15,278permits read
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve it. Cambridge's file we read does not carry a usable application date, so we don't guess at it. Ask the permit office for its current review times.

Finishing the work (measured here): issue → completion. The day the city issued the permit to the day it recorded a final inspection or closeout. That is the contractor's part: doing the work and getting it signed off.

What “finished” means in Cambridge: For contractors with at least 5 permits a year or more old, the share marked complete.

Speed: An estimate of how quickly their permits are marked complete, based on permit status and age, compared with other Cambridge contractors in the trade. Shown for firms with 20+ permits.

By trade

Usual is the middle permit: half finish sooner, half later. Finished is the share of permits a year or more old that the city closed out. A dash means the Cambridge record has no completion date for that trade (siding), so there is nothing to count days from; it does not mean those permits are slow.

TradePermitsUsual days to finishFinishedFirms with 10+ permits
Electrical3,82010471.7%79
Remodel, Addition & Alteration3,51230449.7%38
Plumbing2,9066967.8%72
Gas Fitting2,0574653.8%40
HVAC & Sheet Metal1,47032554.7%24
Roofing7661792.1%8
Solar28411551.0%6
Demolition133697—0
Fire Sprinkler11330893.3%1
New Construction11152430.8%0
Siding106——0

How long each kind of permit takes in Cambridge

Each trade on its own, from issue to the city's sign-off. The spread between the quickest and slowest quarter of firms is the part you can choose.

How long does electrical work take in Cambridge, from permit to sign-off?

The usual electrical permit in Cambridge takes 104 days from issue to the city's final inspection or closeout (3,820 permits, October 2023 through September 2026). 71.7% of electrical permits a year or more old have been closed out. The wait for approval before issue is not in Cambridge's file.

How long does a home remodel take in Cambridge, from permit to sign-off?

The usual remodel, addition & alteration permit in Cambridge takes 304 days from issue to the city's final inspection or closeout (3,512 permits, October 2023 through September 2026). 49.7% of remodel, addition & alteration permits a year or more old have been closed out. The wait for approval before issue is not in Cambridge's file.

How long does plumbing work take in Cambridge, from permit to sign-off?

The usual plumbing permit in Cambridge takes 69 days from issue to the city's final inspection or closeout (2,906 permits, October 2023 through September 2026). 67.8% of plumbing permits a year or more old have been closed out. The quickest quarter of firms usually finish in 0.6 months, the slowest quarter in 4.2 months. The wait for approval before issue is not in Cambridge's file.

0.6 moquickest quarter of firms
3.1 mousual firm
4.2 moslowest quarter of firms

19 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Cambridge plumbing contractors →

How long does gas fitting work take in Cambridge, from permit to sign-off?

The usual gas fitting permit in Cambridge takes 46 days from issue to the city's final inspection or closeout (2,057 permits, October 2023 through September 2026). 53.8% of gas fitting permits a year or more old have been closed out. The quickest quarter of firms usually finish in 0.9 months, the slowest quarter in 11.5 months. The wait for approval before issue is not in Cambridge's file.

0.9 moquickest quarter of firms
1.9 mousual firm
11.5 moslowest quarter of firms

17 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Cambridge gas fitting contractors →

How long does HVAC work take in Cambridge, from permit to sign-off?

The usual HVAC & sheet metal permit in Cambridge takes 325 days from issue to the city's final inspection or closeout (1,470 permits, October 2023 through September 2026). 54.7% of HVAC & sheet metal permits a year or more old have been closed out. The quickest quarter of firms usually finish in 5.2 months, the slowest quarter in 12 months. The wait for approval before issue is not in Cambridge's file.

5.2 moquickest quarter of firms
8 mousual firm
12 moslowest quarter of firms

12 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Cambridge HVAC & sheet metal contractors →

How long does roofing work take in Cambridge, from permit to sign-off?

The usual roofing permit in Cambridge takes 17 days from issue to the city's final inspection or closeout (766 permits, October 2023 through September 2026). 92.1% of roofing permits a year or more old have been closed out. The quickest quarter of firms usually finish in 0 months, the slowest quarter in 0.4 months. The wait for approval before issue is not in Cambridge's file.

0 moquickest quarter of firms
0.4 mousual firm
0.4 moslowest quarter of firms

4 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Cambridge roofing contractors →

How long does solar installation take in Cambridge, from permit to sign-off?

The usual solar permit in Cambridge takes 115 days from issue to the city's final inspection or closeout (284 permits, October 2023 through September 2026). 51.0% of solar permits a year or more old have been closed out. The wait for approval before issue is not in Cambridge's file.

How long does demolition take in Cambridge, from permit to sign-off?

The usual demolition permit in Cambridge takes 697 days from issue to the city's final inspection or closeout (133 permits, October 2023 through September 2026). The wait for approval before issue is not in Cambridge's file.

How long does fire sprinkler work take in Cambridge, from permit to sign-off?

The usual fire sprinkler permit in Cambridge takes 308 days from issue to the city's final inspection or closeout (113 permits, October 2023 through September 2026). 93.3% of fire sprinkler permits a year or more old have been closed out. The wait for approval before issue is not in Cambridge's file.

How long does new home construction take in Cambridge, from permit to sign-off?

The usual new construction permit in Cambridge takes 524 days from issue to the city's final inspection or closeout (111 permits, October 2023 through September 2026). 30.8% of new construction permits a year or more old have been closed out. The wait for approval before issue is not in Cambridge's file.

No completion date or closeout on record for siding, so no answer for that trade.

How these numbers are made

Source: City of Cambridge Inspectional Services permits (the city's per-type open-data permit files). The window is October 2023 through September 2026; a permit filed after that isn't here yet.

A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.

Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits.

Nobody paid to be on this page and nobody can. How the records work in Cambridge →

Common questions

  • What is the permit turnaround in Cambridge?From issue to final inspection or closeout, the usual electrical permit in Cambridge takes 104 days (3,820 permits, October 2023 through September 2026); roofing is quickest at 17 days. The wait to get a permit issued is not in Cambridge's file; ask the permit office for its current review times.
  • How long does it take to get a permit approved in Cambridge?We can't say from the record: Cambridge's file we read has no usable application date, so the approval wait is not in these numbers and we don't estimate it. Every figure on this page runs from the day the permit was issued to the day the city closed it. Ask the permit office for its current review times.
  • Which permits finish fastest in Cambridge?Roofing at 17 days. The slowest is demolition at 697 days. Bigger jobs take longer; so do trades where the final inspection is easy to forget.
  • How many permits actually get finished?It depends on the trade: 93.3% of fire sprinkler permits a year or more old were closed out, against 30.8% for new construction. An open permit can mean unfinished work or a missed final inspection; either one can surface when you sell.
  • Why does an open permit matter to me?An unfinished permit stays on the property, not the contractor. It can hold up a sale or a refinance, and the fix is on you. Ask any contractor you hire to close their permit and show you the final.
  • Can I see this for one contractor?Yes. Every Cambridge electrical contractor is listed with their finished share and time to finish; pick what you value and the list moves. Cambridge permit statistics →

Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis St. Louis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX