How long do permits take in Denver, CO?

The usual demolition permit in Denver, the biggest trade with a completion date, takes 21 days from issue to the city's final inspection or closeout (1,139 permits, October 2023 through September 2026). Demolition is also the quickest trade here; foundation & structural repair the slowest at 93 days. This is the turnaround to finish the work and close the permit, not the wait for approval.

37days, usual across trades
21days, usual demolition permit
91%demolition permits finished
10,375permits read
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve it. Denver's file we read does not carry a usable application date, so we don't guess at it. Ask the permit office for its current review times.

Finishing the work (measured here): issue → completion. The day the city issued the permit to the day it recorded a final inspection or closeout. That is the contractor's part: doing the work and getting it signed off.

What “finished” means in Denver: Only for repair and demolition: Denver stopped recording final dates for most other permits after 2020.

Speed: Only for repair and demolition, for the same reason. Shown for firms with 10+ permits.

By trade

Usual is the middle permit: half finish sooner, half later. Finished is the share of permits a year or more old that the city closed out. A dash means the Denver record has no completion date for that trade (remodel & alteration, new home, garage, addition, pool, shed & outdoor structure, ADU), so there is nothing to count days from; it does not mean those permits are slow.

TradePermitsUsual days to finishFinishedFirms with 10+ permits
Remodel & Alteration3,530——65
New Home2,371——51
Demolition1,1392191.0%11
Garage989——15
Foundation & Structural Repair9519363.7%8
Addition864——8
Pool, Shed & Outdoor Structure269——4
ADU262——2

How long each kind of permit takes in Denver

Each trade on its own, from issue to the city's sign-off. The spread between the quickest and slowest quarter of firms is the part you can choose.

How long does demolition take in Denver, from permit to sign-off?

The usual demolition permit in Denver takes 21 days from issue to the city's final inspection or closeout (1,139 permits, October 2023 through September 2026). 91.0% of demolition permits a year or more old have been closed out. The wait for approval before issue is not in Denver's file.

How long does structural repair work take in Denver, from permit to sign-off?

The usual foundation & structural repair permit in Denver takes 93 days from issue to the city's final inspection or closeout (951 permits, October 2023 through September 2026). 63.7% of foundation & structural repair permits a year or more old have been closed out. The quickest quarter of firms usually finish in 1.3 months, the slowest quarter in 3 months. The wait for approval before issue is not in Denver's file.

1.3 moquickest quarter of firms
3 mousual firm
3 moslowest quarter of firms

7 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Denver foundation & structural repair contractors →

No completion date or closeout on record for remodel & alteration, new home, garage, addition, pool, shed & outdoor structure, ADU, so no answer for those trades.

How these numbers are made

Source: City and County of Denver residential construction and demolition permits. The window is October 2023 through September 2026; a permit filed after that isn't here yet.

A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.

Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits.

Nobody paid to be on this page and nobody can. How the records work in Denver →

Common questions

  • What is the permit turnaround in Denver?From issue to final inspection or closeout, the usual demolition permit in Denver takes 21 days (1,139 permits, October 2023 through September 2026). The wait to get a permit issued is not in Denver's file; ask the permit office for its current review times.
  • How long does it take to get a permit approved in Denver?We can't say from the record: Denver's file we read has no usable application date, so the approval wait is not in these numbers and we don't estimate it. Every figure on this page runs from the day the permit was issued to the day the city closed it. Ask the permit office for its current review times.
  • Which permits finish fastest in Denver?Demolition at 21 days. The slowest is foundation & structural repair at 93 days. Bigger jobs take longer; so do trades where the final inspection is easy to forget.
  • How many permits actually get finished?It depends on the trade: 91.0% of demolition permits a year or more old were closed out, against 63.7% for foundation & structural repair. An open permit can mean unfinished work or a missed final inspection; either one can surface when you sell.
  • Why does an open permit matter to me?An unfinished permit stays on the property, not the contractor. It can hold up a sale or a refinance, and the fix is on you. Ask any contractor you hire to close their permit and show you the final.
  • Can I see this for one contractor?Yes. Every Denver demolition contractor is listed with their finished share and time to finish; pick what you value and the list moves. Denver permit statistics →

Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis St. Louis San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX