The usual electrical permit in Bismarck, the biggest trade with a completion date, takes 233 days from issue to the city's final inspection or closeout (1,669 permits, October 2023 through September 2026). Deck is quickest at 58 days; new home the slowest at 351 days. This is the turnaround to finish the work and close the permit, not the wait for approval.
“How long does a permit take?” can mean two waits. This page measures the second one.
Getting the permit (not measured): application → issue, the wait for the city to approve it. Bismarck's file we read does not carry a usable application date, so we don't guess at it. Ask the permit office for its current review times.
Finishing the work (measured here): issue → completion. The day the city issued the permit to the day it recorded a final inspection or closeout. That is the contractor's part: doing the work and getting it signed off.
What “finished” means in Bismarck: For contractors with at least 5 permits a year or more old, the share the city finaled.
Speed: How long their permits take from issue to the city's finaled date, compared with other Bismarck contractors in the trade. Shown for firms with 10+ permits.
Usual is the middle permit: half finish sooner, half later. Finished is the share of permits a year or more old that the city closed out. A dash means the Bismarck record has no completion date for that trade (furnace & AC replacement), so there is nothing to count days from; it does not mean those permits are slow.
| Trade | Permits | Usual days to finish | Finished | Firms with 10+ permits |
|---|---|---|---|---|
| Furnace & AC Replacement | 2,098 | — | 24.5% | 11 |
| Electrical | 1,669 | 233 | 83.9% | 32 |
| Plumbing | 844 | 277 | 81.7% | 19 |
| HVAC Install | 751 | 142 | 90.3% | 15 |
| New Home | 708 | 351 | 75.4% | 13 |
| Remodel & Addition | 323 | 272 | 72.7% | 5 |
| Fireplace & Stove | 283 | 146 | 77.8% | 4 |
| Deck | 191 | 58 | 85.8% | 3 |
Each trade on its own, from issue to the city's sign-off. The spread between the quickest and slowest quarter of firms is the part you can choose.
The Bismarck record carries no completion date for furnace & AC replacement permits, so we can't count days. 24.5% of furnace & AC replacement permits a year or more old have been closed out. That is from 2,098 permits, October 2023 through September 2026. The wait for approval before issue is not in Bismarck's file.
The usual electrical permit in Bismarck takes 233 days from issue to the city's final inspection or closeout (1,669 permits, October 2023 through September 2026). 83.9% of electrical permits a year or more old have been closed out. The quickest quarter of firms usually finish in 2.1 months, the slowest quarter in 8.4 months. The wait for approval before issue is not in Bismarck's file.
31 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Bismarck electrical contractors →
The usual plumbing permit in Bismarck takes 277 days from issue to the city's final inspection or closeout (844 permits, October 2023 through September 2026). 81.7% of plumbing permits a year or more old have been closed out. The quickest quarter of firms usually finish in 7.9 months, the slowest quarter in 9.8 months. The wait for approval before issue is not in Bismarck's file.
16 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Bismarck plumbing contractors →
The usual HVAC install permit in Bismarck takes 142 days from issue to the city's final inspection or closeout (751 permits, October 2023 through September 2026). 90.3% of HVAC install permits a year or more old have been closed out. The quickest quarter of firms usually finish in 4.4 months, the slowest quarter in 5.8 months. The wait for approval before issue is not in Bismarck's file.
14 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Bismarck HVAC install contractors →
The usual new home permit in Bismarck takes 351 days from issue to the city's final inspection or closeout (708 permits, October 2023 through September 2026). 75.4% of new home permits a year or more old have been closed out. The quickest quarter of firms usually finish in 9.9 months, the slowest quarter in 13.3 months. The wait for approval before issue is not in Bismarck's file.
12 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Bismarck new home contractors →
The usual remodel & addition permit in Bismarck takes 272 days from issue to the city's final inspection or closeout (323 permits, October 2023 through September 2026). 72.7% of remodel & addition permits a year or more old have been closed out. The wait for approval before issue is not in Bismarck's file.
The usual fireplace & stove permit in Bismarck takes 146 days from issue to the city's final inspection or closeout (283 permits, October 2023 through September 2026). 77.8% of fireplace & stove permits a year or more old have been closed out. The quickest quarter of firms usually finish in 4.6 months, the slowest quarter in 4.8 months. The wait for approval before issue is not in Bismarck's file.
4 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Bismarck fireplace & stove contractors →
The usual deck permit in Bismarck takes 58 days from issue to the city's final inspection or closeout (191 permits, October 2023 through September 2026). 85.8% of deck permits a year or more old have been closed out. The quickest quarter of firms usually finish in 0.5 months, the slowest quarter in 1.1 months. The wait for approval before issue is not in Bismarck's file.
3 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Bismarck deck contractors →
Source: City of Bismarck TRAKiT building, mechanical, electrical and plumbing permits on homes. The window is October 2023 through September 2026; a permit filed after that isn't here yet.
A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.
Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits.
Nobody paid to be on this page and nobody can. How the records work in Bismarck →
Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis St. Louis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX