How long do permits take in Provo, UT?

The usual new home construction permit in Provo, the biggest trade with a completion date, takes 254 days from issue to the city's final inspection or closeout (458 permits, October 2023 through September 2026). Remodel is quickest at 227 days; solar the slowest at 925 days. This is the turnaround to finish the work and close the permit, not the wait for approval.

305days, usual across trades
254days, usual new home construction permit
87%new home construction permits finished
1,149permits read
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve it. Provo's file we read does not carry a usable application date, so we don't guess at it. Ask the permit office for its current review times.

Finishing the work (measured here): issue → completion. The day the city issued the permit to the day it recorded a final inspection or closeout. That is the contractor's part: doing the work and getting it signed off.

What “finished” means in Provo: For contractors with at least 5 permits a year or more old, the share that Provo City closed within a year of issue.

Speed: How long their permits take from issue to the city's finalized date, compared with other Provo contractors in the trade. Shown for firms with 10+ permits.

By trade

Usual is the middle permit: half finish sooner, half later. Finished is the share of permits a year or more old that the city closed out. A dash means the Provo record has no completion date for that trade (re-roof), so there is nothing to count days from; it does not mean those permits are slow.

TradePermitsUsual days to finishFinishedFirms with 10+ permits
New Home Construction45825487.3%10
Re-Roof286—36.1%6
Remodel22622761.4%1
Solar17992519.3%6

How long each kind of permit takes in Provo

Each trade on its own, from issue to the city's sign-off. The spread between the quickest and slowest quarter of firms is the part you can choose.

How long does new home construction take in Provo, from permit to sign-off?

The usual new home construction permit in Provo takes 254 days from issue to the city's final inspection or closeout (458 permits, October 2023 through September 2026). 87.3% of new home construction permits a year or more old have been closed out. The quickest quarter of firms usually finish in 6.1 months, the slowest quarter in 7 months. The wait for approval before issue is not in Provo's file.

6.1 moquickest quarter of firms
7 mousual firm
7 moslowest quarter of firms

8 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Provo new home construction contractors →

How long does roofing work take in Provo, from permit to sign-off?

The Provo record carries no completion date for re-roof permits, so we can't count days. 36.1% of re-roof permits a year or more old have been closed out. That is from 286 permits, October 2023 through September 2026. The wait for approval before issue is not in Provo's file.

How long does a home remodel take in Provo, from permit to sign-off?

The usual remodel permit in Provo takes 227 days from issue to the city's final inspection or closeout (226 permits, October 2023 through September 2026). 61.4% of remodel permits a year or more old have been closed out. The wait for approval before issue is not in Provo's file.

How long does solar installation take in Provo, from permit to sign-off?

The usual solar permit in Provo takes 925 days from issue to the city's final inspection or closeout (179 permits, October 2023 through September 2026). 19.3% of solar permits a year or more old have been closed out. The quickest quarter of firms usually finish in 27.3 months, the slowest quarter in 32 months. The wait for approval before issue is not in Provo's file.

27.3 moquickest quarter of firms
30.4 mousual firm
32 moslowest quarter of firms

3 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Provo solar contractors →

How these numbers are made

Source: Provo City building permits on single-family homes, two-family homes, townhomes and condos (one record per permit number). The window is October 2023 through September 2026; a permit filed after that isn't here yet.

A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.

Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits.

Nobody paid to be on this page and nobody can. How the records work in Provo →

Common questions

  • What is the permit turnaround in Provo?From issue to final inspection or closeout, the usual new home construction permit in Provo takes 254 days (458 permits, October 2023 through September 2026); remodel is quickest at 227 days. The wait to get a permit issued is not in Provo's file; ask the permit office for its current review times.
  • How long does it take to get a permit approved in Provo?We can't say from the record: Provo's file we read has no usable application date, so the approval wait is not in these numbers and we don't estimate it. Every figure on this page runs from the day the permit was issued to the day the city closed it. Ask the permit office for its current review times.
  • Which permits finish fastest in Provo?Remodel at 227 days. The slowest is solar at 925 days. Bigger jobs take longer; so do trades where the final inspection is easy to forget.
  • How many permits actually get finished?It depends on the trade: 87.3% of new home construction permits a year or more old were closed out, against 19.3% for solar. An open permit can mean unfinished work or a missed final inspection; either one can surface when you sell.
  • Why does an open permit matter to me?An unfinished permit stays on the property, not the contractor. It can hold up a sale or a refinance, and the fix is on you. Ask any contractor you hire to close their permit and show you the final.
  • Can I see this for one contractor?Yes. Every Provo new home construction contractor is listed with their finished share and time to finish; pick what you value and the list moves. Provo permit statistics →

Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis St. Louis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Naperville Bellevue Cape Coral Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX