How long do permits take in Orlando, FL?

The usual Orlando permit takes 85 days from issue to the city's final inspection or closeout, across all 12 kinds of work on file (42,936 permits, October 2023 through September 2026). The usual roofing permit, the biggest trade here, takes 27 days. Roofing is also the quickest trade here; home addition the slowest at 238 days. This is the turnaround to finish the work and close the permit, not the wait for approval.

85days, usual across trades
27days, usual roofing permit
42,936permits read
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve it. Orlando's file we read does not carry a usable application date, so we don't guess at it. Ask the permit office for its current review times.

Finishing the work (measured here): issue → completion. The day the city issued the permit to the day it recorded a final inspection or closeout. That is the contractor's part: doing the work and getting it signed off.

Speed: How long their permits take to reach final inspection, from issue date, compared with other Orlando contractors in the trade. Shown for firms with 10+ permits.

By trade

Usual is the middle permit: half finish sooner, half later. Finished is the share of permits a year or more old that the city closed out.

TradePermitsUsual days to finishFirms with 10+ permits
Roofing9,81827192
HVAC / Gas8,26991122
Electrical7,076127116
Plumbing6,07512391
Remodel & Repair4,7165981
New Home3,10720328
Solar1,0154234
Fence9105518
Swimming Pool86419821
Demolition474629
Home Addition3342380
Shed, Garage & Accessory278484

How long each kind of permit takes in Orlando

Each trade on its own, from issue to the city's sign-off. The spread between the quickest and slowest quarter of firms is the part you can choose.

How long does roofing work take in Orlando, from permit to sign-off?

The usual roofing permit in Orlando takes 27 days from issue to the city's final inspection or closeout (9,818 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 0.6 months, the slowest quarter in 2.1 months. The wait for approval before issue is not in Orlando's file.

0.6 moquickest quarter of firms
0.8 mousual firm
2.1 moslowest quarter of firms

189 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Orlando roofing contractors →

How long does HVAC work take in Orlando, from permit to sign-off?

The usual HVAC / gas permit in Orlando takes 91 days from issue to the city's final inspection or closeout (8,269 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 1.3 months, the slowest quarter in 3.6 months. The wait for approval before issue is not in Orlando's file.

1.3 moquickest quarter of firms
3.2 mousual firm
3.6 moslowest quarter of firms

117 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Orlando HVAC / gas contractors →

How long does electrical work take in Orlando, from permit to sign-off?

The usual electrical permit in Orlando takes 127 days from issue to the city's final inspection or closeout (7,076 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 1.7 months, the slowest quarter in 5.5 months. The wait for approval before issue is not in Orlando's file.

1.7 moquickest quarter of firms
4.4 mousual firm
5.5 moslowest quarter of firms

113 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Orlando electrical contractors →

How long does plumbing work take in Orlando, from permit to sign-off?

The usual plumbing permit in Orlando takes 123 days from issue to the city's final inspection or closeout (6,075 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 0.5 months, the slowest quarter in 4.9 months. The wait for approval before issue is not in Orlando's file.

0.5 moquickest quarter of firms
4.2 mousual firm
4.9 moslowest quarter of firms

88 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Orlando plumbing contractors →

How long does a home remodel take in Orlando, from permit to sign-off?

The usual remodel & repair permit in Orlando takes 59 days from issue to the city's final inspection or closeout (4,716 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 1.3 months, the slowest quarter in 2.1 months. The wait for approval before issue is not in Orlando's file.

1.3 moquickest quarter of firms
1.5 mousual firm
2.1 moslowest quarter of firms

75 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Orlando remodel & repair contractors →

How long does new home construction take in Orlando, from permit to sign-off?

The usual new home permit in Orlando takes 203 days from issue to the city's final inspection or closeout (3,107 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 5.6 months, the slowest quarter in 7.8 months. The wait for approval before issue is not in Orlando's file.

5.6 moquickest quarter of firms
6.3 mousual firm
7.8 moslowest quarter of firms

25 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Orlando new home contractors →

How long does solar installation take in Orlando, from permit to sign-off?

The usual solar permit in Orlando takes 42 days from issue to the city's final inspection or closeout (1,015 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 0.9 months, the slowest quarter in 2.1 months. The wait for approval before issue is not in Orlando's file.

0.9 moquickest quarter of firms
1.4 mousual firm
2.1 moslowest quarter of firms

32 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Orlando solar contractors →

How long does fence installation take in Orlando, from permit to sign-off?

The usual fence permit in Orlando takes 55 days from issue to the city's final inspection or closeout (910 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 1 month, the slowest quarter in 2.2 months. The wait for approval before issue is not in Orlando's file.

1 moquickest quarter of firms
1.6 mousual firm
2.2 moslowest quarter of firms

18 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Orlando fence contractors →

How long does a pool build take in Orlando, from permit to sign-off?

The usual swimming pool permit in Orlando takes 198 days from issue to the city's final inspection or closeout (864 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 5.3 months, the slowest quarter in 7.1 months. The wait for approval before issue is not in Orlando's file.

5.3 moquickest quarter of firms
6.1 mousual firm
7.1 moslowest quarter of firms

20 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Orlando swimming pool contractors →

How long does demolition take in Orlando, from permit to sign-off?

The usual demolition permit in Orlando takes 62 days from issue to the city's final inspection or closeout (474 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 1.4 months, the slowest quarter in 3.1 months. The wait for approval before issue is not in Orlando's file.

1.4 moquickest quarter of firms
1.7 mousual firm
3.1 moslowest quarter of firms

9 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Orlando demolition contractors →

How long does a home addition take in Orlando, from permit to sign-off?

The usual home addition permit in Orlando takes 238 days from issue to the city's final inspection or closeout (334 permits, October 2023 through September 2026). The wait for approval before issue is not in Orlando's file.

How long does garage and accessory building work take in Orlando, from permit to sign-off?

The usual shed, garage & accessory permit in Orlando takes 48 days from issue to the city's final inspection or closeout (278 permits, October 2023 through September 2026). The wait for approval before issue is not in Orlando's file.

How these numbers are made

Source: City of Orlando building permits for one- and two-family homes. The window is October 2023 through September 2026; a permit filed after that isn't here yet.

A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.

Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits.

Nobody paid to be on this page and nobody can. How the records work in Orlando →

Common questions

  • What is the permit turnaround in Orlando?From issue to final inspection or closeout, the usual roofing permit in Orlando takes 27 days (9,818 permits, October 2023 through September 2026). The wait to get a permit issued is not in Orlando's file; ask the permit office for its current review times.
  • How long does it take to get a permit approved in Orlando?We can't say from the record: Orlando's file we read has no usable application date, so the approval wait is not in these numbers and we don't estimate it. Every figure on this page runs from the day the permit was issued to the day the city closed it. Ask the permit office for its current review times.
  • Which permits finish fastest in Orlando?Roofing at 27 days. The slowest is home addition at 238 days. Bigger jobs take longer; so do trades where the final inspection is easy to forget.
  • Why does an open permit matter to me?An unfinished permit stays on the property, not the contractor. It can hold up a sale or a refinance, and the fix is on you. Ask any contractor you hire to close their permit and show you the final.
  • Can I see this for one contractor?Yes. Every Orlando roofing contractor is listed with their finished share and time to finish; pick what you value and the list moves. Orlando permit statistics →

Other cities: Nashville New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis St. Louis Denver San Diego Colorado Springs Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX