How long do permits take in Colorado Springs, CO?

The usual Colorado Springs permit takes 32 days from issue to the city's final inspection or closeout, across all 12 kinds of work on file (101,680 permits, October 2023 through September 2026). The usual roofing permit, the biggest trade here, takes 41 days. Plumbing is quickest at 19 days; new home the slowest at 190 days. This is the turnaround to finish the work and close the permit, not the wait for approval.

32days, usual across trades
41days, usual roofing permit
101,680permits read
Sep 2026records through

Getting the permit vs finishing the work: two different clocks

“How long does a permit take?” can mean two waits. This page measures the second one.

Getting the permit (not measured): application → issue, the wait for the city to approve it. Colorado Springs's file we read does not carry a usable application date, so we don't guess at it. Ask the permit office for its current review times.

Finishing the work (measured here): issue → completion. The day the city issued the permit to the day it recorded a final inspection or closeout. That is the contractor's part: doing the work and getting it signed off.

Speed: An estimate of how quickly their permits are finaled, based on permit status and age, compared with other Colorado Springs contractors in the trade. Shown for firms with 20+ permits.

By trade

Usual is the middle permit: half finish sooner, half later. Finished is the share of permits a year or more old that the city closed out.

TradePermitsUsual days to finishFirms with 10+ permits
Roofing23,50841318
HVAC & Mechanical22,48521231
Electrical22,29726260
Plumbing18,39919208
New Home4,27419032
Solar3,0354149
Deck, Patio Cover & Pergola2,5315455
Remodel & Addition1,6399635
Siding & Stucco1,5984528
Foundation & Structural Repair1,1769810
Basement Finish602814
Garage & Accessory Building1361333

How long each kind of permit takes in Colorado Springs

Each trade on its own, from issue to the city's sign-off. The spread between the quickest and slowest quarter of firms is the part you can choose.

How long does roofing work take in Colorado Springs, from permit to sign-off?

The usual roofing permit in Colorado Springs takes 41 days from issue to the city's final inspection or closeout (23,508 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 0.7 months, the slowest quarter in 1.6 months. The wait for approval before issue is not in Colorado Springs's file.

0.7 moquickest quarter of firms
1 mousual firm
1.6 moslowest quarter of firms

228 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Colorado Springs roofing contractors →

How long does HVAC work take in Colorado Springs, from permit to sign-off?

The usual HVAC & mechanical permit in Colorado Springs takes 21 days from issue to the city's final inspection or closeout (22,485 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 0.1 months, the slowest quarter in 0.7 months. The wait for approval before issue is not in Colorado Springs's file.

0.1 moquickest quarter of firms
0.4 mousual firm
0.7 moslowest quarter of firms

171 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Colorado Springs HVAC & mechanical contractors →

How long does electrical work take in Colorado Springs, from permit to sign-off?

The usual electrical permit in Colorado Springs takes 26 days from issue to the city's final inspection or closeout (22,297 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 0.4 months, the slowest quarter in 0.9 months. The wait for approval before issue is not in Colorado Springs's file.

0.4 moquickest quarter of firms
0.6 mousual firm
0.9 moslowest quarter of firms

190 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Colorado Springs electrical contractors →

How long does plumbing work take in Colorado Springs, from permit to sign-off?

The usual plumbing permit in Colorado Springs takes 19 days from issue to the city's final inspection or closeout (18,399 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 0.1 months, the slowest quarter in 0.7 months. The wait for approval before issue is not in Colorado Springs's file.

0.1 moquickest quarter of firms
0.4 mousual firm
0.7 moslowest quarter of firms

150 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Colorado Springs plumbing contractors →

How long does new home construction take in Colorado Springs, from permit to sign-off?

The usual new home permit in Colorado Springs takes 190 days from issue to the city's final inspection or closeout (4,274 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 3.6 months, the slowest quarter in 5.6 months. The wait for approval before issue is not in Colorado Springs's file.

3.6 moquickest quarter of firms
4.6 mousual firm
5.6 moslowest quarter of firms

26 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Colorado Springs new home contractors →

How long does solar installation take in Colorado Springs, from permit to sign-off?

The usual solar permit in Colorado Springs takes 41 days from issue to the city's final inspection or closeout (3,035 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 0 months, the slowest quarter in 1.4 months. The wait for approval before issue is not in Colorado Springs's file.

0 moquickest quarter of firms
1.1 mousual firm
1.4 moslowest quarter of firms

33 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Colorado Springs solar contractors →

How long does a deck build take in Colorado Springs, from permit to sign-off?

The usual deck, patio cover & pergola permit in Colorado Springs takes 54 days from issue to the city's final inspection or closeout (2,531 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 1.2 months, the slowest quarter in 2.1 months. The wait for approval before issue is not in Colorado Springs's file.

1.2 moquickest quarter of firms
1.5 mousual firm
2.1 moslowest quarter of firms

25 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Colorado Springs deck, patio cover & pergola contractors →

How long does a home remodel take in Colorado Springs, from permit to sign-off?

The usual remodel & addition permit in Colorado Springs takes 96 days from issue to the city's final inspection or closeout (1,639 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 2 months, the slowest quarter in 3.3 months. The wait for approval before issue is not in Colorado Springs's file.

2 moquickest quarter of firms
2.5 mousual firm
3.3 moslowest quarter of firms

9 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Colorado Springs remodel & addition contractors →

How long does siding work take in Colorado Springs, from permit to sign-off?

The usual siding & stucco permit in Colorado Springs takes 45 days from issue to the city's final inspection or closeout (1,598 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 0.4 months, the slowest quarter in 1.7 months. The wait for approval before issue is not in Colorado Springs's file.

0.4 moquickest quarter of firms
1.1 mousual firm
1.7 moslowest quarter of firms

15 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Colorado Springs siding & stucco contractors →

How long does foundation work take in Colorado Springs, from permit to sign-off?

The usual foundation & structural repair permit in Colorado Springs takes 98 days from issue to the city's final inspection or closeout (1,176 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 1.6 months, the slowest quarter in 4.3 months. The wait for approval before issue is not in Colorado Springs's file.

1.6 moquickest quarter of firms
3.5 mousual firm
4.3 moslowest quarter of firms

8 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Colorado Springs foundation & structural repair contractors →

How long does basement finishing work take in Colorado Springs, from permit to sign-off?

The usual basement finish permit in Colorado Springs takes 81 days from issue to the city's final inspection or closeout (602 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 1.7 months, the slowest quarter in 3.2 months. The wait for approval before issue is not in Colorado Springs's file.

1.7 moquickest quarter of firms
1.7 mousual firm
3.2 moslowest quarter of firms

2 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Colorado Springs basement finish contractors →

How long does garage construction take in Colorado Springs, from permit to sign-off?

The usual garage & accessory building permit in Colorado Springs takes 133 days from issue to the city's final inspection or closeout (136 permits, October 2023 through September 2026). The quickest quarter of firms usually finish in 4.1 months, the slowest quarter in 5.1 months. The wait for approval before issue is not in Colorado Springs's file.

4.1 moquickest quarter of firms
4.1 mousual firm
5.1 moslowest quarter of firms

2 firms with enough permits to measure, each firm's usual months to finish, weighted by its permits. Compare Colorado Springs garage & accessory building contractors →

How these numbers are made

Source: Pikes Peak Regional Building Department permits inside Colorado Springs city limits. The window is October 2023 through September 2026; a permit filed after that isn't here yet.

A filed value is what the contractor wrote on the permit when they applied. It is not a quote and not the final bill.

Counts are permits, not jobs: one job can need several permits, and one permit can cover several visits.

Nobody paid to be on this page and nobody can. How the records work in Colorado Springs →

Common questions

  • What is the permit turnaround in Colorado Springs?From issue to final inspection or closeout, the usual roofing permit in Colorado Springs takes 41 days (23,508 permits, October 2023 through September 2026); plumbing is quickest at 19 days. The wait to get a permit issued is not in Colorado Springs's file; ask the permit office for its current review times.
  • How long does it take to get a permit approved in Colorado Springs?We can't say from the record: Colorado Springs's file we read has no usable application date, so the approval wait is not in these numbers and we don't estimate it. Every figure on this page runs from the day the permit was issued to the day the city closed it. Ask the permit office for its current review times.
  • Which permits finish fastest in Colorado Springs?Plumbing at 19 days. The slowest is new home at 190 days. Bigger jobs take longer; so do trades where the final inspection is easy to forget.
  • Why does an open permit matter to me?An unfinished permit stays on the property, not the contractor. It can hold up a sale or a refinance, and the fix is on you. Ask any contractor you hire to close their permit and show you the final.
  • Can I see this for one contractor?Yes. Every Colorado Springs roofing contractor is listed with their finished share and time to finish; pick what you value and the list moves. Colorado Springs permit statistics →

Other cities: Nashville Orlando New York City Chicago Austin Raleigh Cincinnati Cleveland Pittsburgh Miami Minneapolis St. Louis Denver San Diego Honolulu Albuquerque Boulder Greensboro Saint Paul Arlington, VA Scottsdale Henderson Cambridge Somerville Cary Mesa Naperville Bellevue Cape Coral Provo Palo Alto Bellingham Bend Ames Denton Sugar Land Burlington, VT Seattle San Francisco Medford Anaheim Elk Grove Wilmington, NC Bismarck Tyler, TX Columbus, OH Wheaton, IL San Diego County (unincorporated) Marin County (unincorporated) Sacramento County (unincorporated) Citrus Heights, CA Waco, TX